Project Details
This project included a new intersection and dedicated turning lanes, lighting solutions, drainage improvements, construction of a 1.2km eastbound overtaking lane and resealing surfaces.
- Culvert construction
- Pavement drainage
- Subsoil drainage
- 33,000m2 Clearing and grubbing
- 13,580m3 road excavation
- 5,895m3 stabilisation with plant mixed foamed bitumen
- Mill existing material and dispose – 18,920m2
- Sprayed bituminous surface – 58,500 litre
- Removal and storage road furniture
- Signage
- Guardrails
- Linemarking
- Landscaping and stockpile remediation
Pavement required the use of plant mixed foam bitumen, new technology brought out by the Department of Transport and Main Roads.
The project was delivered 2 weeks ahead of schedule.
Client:
D’Aguilar Highway Safety and Improvements and RehabilitationProject Value:
$7.4 millionProject Start:
November 2015Project Completion:
August 2016Principle Contractor:
McIlwain