Project Details

WW Surveys provided survey management and structural survey services for this greenfield project.

The project included the construction of 6 km of multi-lane motorway with four bridges and an interchange at Lomandra Drive, which was predominately built on a soft soil environment.

Along with supplying survey services, WW Surveys was also successfully involved in the design interface of the project. We worked with the design, client and construction teams to overcome the day-to-day challenges inherent to a project of this calibre.

Client:
Brisbane Airport Corporation
Project Value:
$209 million
Project Start:
October 2006
Project Completion:
December 2009
Principle Contractor:
Leighton Contractors, Queensland