Project Details
The Woolgoolga to Ballina Pacific Highway upgrade involved the duplication of 155 kilometres to a four-lane divided road, starting 6 kilometres north of Woolgoolga (north of Coffs Harbour) and ends 6 kilometres south of Ballina.
The Maclean cut project was a variation of the Woodburn to Broadwater service road project.
Construction of pavement crossovers and widening
- Cleaning, grubbing, topsoil stripping and bulk earthworks;
- Foundation works and select and upper zone material placement;
- Installation of all required drainage and scour protection;
- Installation of permanent fencing and road furniture including guide posts and F-type barrier.
Yamba interchange preload and foundation treatment
- Removal of the existing pavement;
- Foundation treatments including installation of drainage layer and wick drains;
- Placement of surcharge materials;
- Installation of surcharge monitoring equipment;
- Installation of required temporary and permanent drainage;
- Temporary stabilisation of earth embankments.
The Maclean cut project purpose was to facilitate future growing traffic and prepare the land for the Yamba interchange area.
Client:
Australian and NSW Governments, Road and Maritime Services | Pacific CompleteProject Value:
$17.9 millionProject Start:
N/AProject Completion:
August 2019Principle Contractor:
See Civil