Project Details
The Section 5 earthworks stage of the upgrade included the construction of the northbound and southbound carriageways as well as interchange ramps and local roads, north of the Harwood Bridge.
- Completion of around 50,000 cubic metres of earthworks across both carriageways and local roads and interchange ramps.
- Placement of 40,000 cubic metres of select and verge materials
- Removal of surcharge materials at the appropriate point through liaison with the project client and neighbouring contractors.
- Significant liaison with neighbouring contractors to ensuring works could be managed collaboratively and efficiently
- Facilitating the switching of traffic onto the completed Hardwood Bridge, a major milestone for the overall Section 5 works
- Removal of redundant pavements once traffic changes have been made
Correct planning of the earthwork by surveyors maximised the quality of the project.
Client:
Australian and NSW Governments, Road and Maritime Services | Pacific CompleteProject Value:
$25 millionProject Start:
October 2019Project Completion:
February 2020Principle Contractor:
See Civil