Westfield Northlakes

Project Details

The aim of the upgrade was to facilitate vehicle and pedestrian movements around Anzac Avenue and the shopping precinct.

  • Lane widening for an off-ramp from Anzac Avenue (major arterial road) using TMR specifications
  • Staged construction of the off-ramp under live traffic conditions
  • Construction of a concrete pedestrian and cyclist access bridge off Anzac Avenue into the new Westfield complex
  • Upgrades to street lighting and traffic signals including the installation of an overhead steel gantry, delivered under live traffic.
Client:
Scentre Design and Construction
Project Value:
$4.3 million
Project Start:
N/A
Project Completion:
October 2016
Principle Contractor:
See Civil